Build Timeline
Total contract days remaining
- Land Deposit Paid - February 2014
- Construction Deposit Paid - 24/05/2014
- Tender Appointment - 23/07/2014
- Colour, Electrical & Tiles Appointment - 15/09/2014
- Contract Appointment - 29/09/2014
- Land Settlement - 23/12/2014
- Building Permit Issued - 05/02/2015
- Official Site Start - 16/02/2015
- Framing Started- 16/03/2015
- Frame Completed- 01/04/2015
- Roof Completed- 24/04/2015
- Bricking Started- 12/05/2015
- Bricking Completed-11/06/2015
- Lock-up & Fixing complete - 15/06/2015
- Practical Completion Inspection (PCI) - 08/09/2015