Friday 3 April 2015

Frame inspection - Not impressed!

It all started with one email, advising us that our frame had been completed and to pay up. I immediately responded and advised that as with the base stage payment, we will not be making any payments until all issues (specifically defects that don't mean the BCA guidelines) are resolved.

Porter Davis staff were very hesitant at accepting this and said they will discuss it with management. The response was "We can't accept payments to be held because of MINOR issues". Minor you say...? I don't think so!

Luckily I stuck to my guns, as yesterday I got a call from a very concerned Independent Inspector which was followed by a frame/slab stage report that took away all the excitement from the progress on our build.

The report is too long and has too much confidential information to post on the blog but here is a summary of the defects picked up:

  • Number of intersecting wall block connections not nailed off - Apparently a common one for Porter Davis

  • H2 rated timber installed to the front of the garage. It will be below FGL (Finished Ground Level) so needs to be H4 timber. 
  • Timber sheet bracing defective as it does not meet the requirement of being secured at a maximum of 150 mm centres. 

  • Slab to the front right hand corner of the house has been damaged and 'broken away'. It will not support the weight of the bricks and needs to be rectified. Engineering needs to be done, site surveyor has to be sent this documentation and he/she must witness the opening and closing of the slab edge.

  • RHS of the porch still needs the concrete 'refilled' 

  • Bath void still has a hole exposing the foam pods and therefore is a termite barrier issue
  • The timber to the porch need to be H3 hazard rated. Only H2 rated timber installed. 
  • Windows above 1800 mm in height must be secured at a minimum of 3 points to the frame and supported in the frame via packets. This is specified by the manufacturer of the windows. The installation does not meet this requirement. 
  • Extra support required for the alcove in the study wall due to length being over 1800 mm

  • Gang nails universal brackets not secured sufficiently. Missing nails.

  • Some trusses installed the wrong way around! 

  • Over 10 trusses out of plumb. They are installed at a greater than 50 mm out of plumb, especially to the rear of the house.


I am not sure how they managed to get our frame 'signed off'' with defects such as these. I have a sent a very serious email to our BC with the required parties CC'ed requesting the defects to be rectified before any further progress to our build. I have also (once again) made it very clear that I will not authorise any payments until we have supporting evidence in writing that the defects have been attended too. 

We will most likely get our independent inspector back out to re-check all these defects have been resolved as requested before going any further. Even though this will cost us even more, I think it's value added considering the situation we are faced with. 

Thanks for reading the super long post! 

5 comments:

  1. I'm sorry to hear this news Joe... keep us informed how you get on.

    ReplyDelete
    Replies
    1. Thanks Brenton... I hope to have some better news in the coming weeks.

      Delete
  2. Sorry to hear these Mate !!! hope everything will be sorted for u soon! im a bit worried now too! :-(

    ReplyDelete
  3. Hey Joe ! Could you plz tell me about hiring an independent inspector ?Is it expensive ?

    ReplyDelete
  4. Hi Daz,

    Thank you, so do I!

    There's no need to worry, PD will definitely sort the issues out. It's just a matter or picking then up.

    Not really in the scheme of things. You would be up for about 2k. That's nothing compared to the total investment IMO.

    Cheers

    ReplyDelete