After reviewing our floor levels today I noticed that Porter Davis has reduced the total house level by 200 mm between our contract and final construction drawings. We missed this when we were checking our construction drawings. We were also not informed of this change at any point!

Here is a comparison of the two drawings. Hoping to have an answer for this first thing tomorrow morning.