Wednesday 29 April 2015

In-wall plumbing complete

Went past the house this morning and noticed that all the internal wall plumbing has been completed and lock-up crew has started to 'straighten' the walls and do other various jobs like clean up and build the bath HOB.

I noticed that the cold water tap to the fridge space is missing so I will be raising that to the SS. Also, the HWS has not been moved as we requested in the drawings. I think it's mainly because the new location is not possible due to the shower plumbing being on the other side.

Study water points installed. Need to get them moved further to the left as originally requested.

Bulkhead to master bedroom door removed to be raised.
 En-suite



Kitchen island

 Kitchen wall bench-top

 Bathroom plumbing and bath HOB



 Laundry

Gas and water point for alfresco

 Hot water service and gas feed line

No comments:

Post a Comment